Designating Working Days in Scheduling

Designate working days and holidays to customize your schedule according to the demands of the project.

  1. In an open schedule, go to Tools > Options and select the Working Days tab.

  2. Select the days of the week that are work days.

  3. To designate holidays, select Account for Holidays in Schedule. Select the holidays that will not be scheduled as work days.

  4. Click OK.